Wall frames for all townhouses have been completed, marking progress in our infrastructure. Framing inspection is the next step, ensuring quality…
The Davis, Nov 2018
We are pleased to provide the progress achieved on site to date for The Davis.
– Ground floor stab is completed.
– Wall framing to the ground floor is completed. First-floor framing underway.
– Structural steel has commenced.
– Plaster/shaft liner has commenced.
– Insulation installation to basement ceiling has commenced.
– Civil drainage works have continued.
– Hydraulic and electrical cast in/rough us underway.
Construction completion is still on track to be August 2019.