Ashton Park, August 2018

  |  Construction Updates

We are pleased to provide you with the progress achieved on site so far.

The following tasks, operations and processes were performed in the current period;

Below ground works:
o Hydraulics & Civil works – COMPLETE
o Electrical works including NBN – COMPLETE & READY FOR CONNECTION
o Authority Connections works – IN PROGRESS

Ground Floor:
o Ground Floor Concrete Slab preparations (Building B) – COMPLETE
o Ground Floor Concrete Slab preparations (Building A) – IN PROGRESS
o Structural block walls (Building B) – COMPLETE
o Structural block walls (Building A) – COMPLETE
o Formwork to Level 1 (Building B) – COMPLETE

Other:
o Steel framing (Building B) – in production
o Steel framing (Building A) – Shop drawings in progress

Ashton Park Ashton Park Ashton Park Ashton Park Ashton Park